Main features used in Aramchan Bridge
- Seismic analysis
- Construction stage analysis with transverse model
- Detail analysis with finite elements
Project Information
- Owner
- Korea Land and Housing Corporation
- General Contractor
- SK E&C
- Engineering Consultant
- SAMBO Engineering
- Construction Period
- 2011 – 2015
- Type of Project
- Cable-stayed Bridge
- Size of Structure
- 250m Main Span, 840m Total Length
- Location
- Sejong, Korea
- Used Product
- MIDAS CIVIL
- Modeling
- Result
- Construction
- Panorama
Aramchan bridge is the first open-type high-altitude pylon cable-stayed bridge in South Korea that designed and built the pylon in U shape to connect the pylon in 114m long with the curse tower (83m) asymmetrically and maximize beauty and River’s safety.
Project Contact
- Engineering Consultant
- SAMBO Engineering
- Address
- SAMBO Engineering
- Introduction
- Sambo Engineering & Construction Company provides construction and civil engineering services internationally. The company specializes in foundation engineering including grouting and boring.
- Website
- http://www.samboeng.co.kr/
- -