Main features used in Decking of Sungei Ketapang
- Moving load analysis with standard and user-defined vehicle loads
- Construction stage analysis with composite action
Project Information
- Owner
- Land Transport Authority of Singapore (LTA)
- General Contractor
- HSL Constructor
- Engineering Consultant
- WRX Engineers
- Construction Period
- Completed in 2016
- Type of Project
- PSC Composite Girder Bridge
- Size of Structure
- 12m Main Span, 650m Total Length
- Location
- Singapore
- Used Product
- MIDAS CIVIL
- Modeling
- Result
- Construction
The Decking of Sungei Ketapang (LTA-T3009) serves to ease the vehicular movement in and out
of the Laguna National Golf & Country Club into the busy Xilin Avenue and Changi South Avenue 3,
when Laguna Golf Green Road has to make way for the tunneling work for the future Downtown
Line (DTL). Prior to the marine piling work, Sungei Ketapang is the first widened to ensure that
marine piling and steel structure works will not obstruct the canal water flow.
Project Contact
- Engineering Consultant
- WRX Engineers
- Address
- 190 Middle Road #18-05 Fortune Centre, 188979, Singapore
- Introduction
- WRX Consultants and WRX Engineers Pte Ltd are civil & structural consultancy firm specialize in project management, civil and structural works.
- Website
- https://www.wrx.com.sg
- wrxeng@wrx.com.sg