Main features used in Greystone Footbridge
- Construction staged analysis
- Unknown load factor and lack of fit force for cable optimization
- Dynamic analysis
Project Information
- Owner
- Knowsley Council
- General Contractor
- Eric Wright Civil Engineering
- Engineering Consultant
- WSP | Parsons Brinckerhoff
- Construction Period
- Completed in 2015
- Type of Project
- Cable-stayed Bridge
- Size of Structure
- 40m Main Span, 80m Total Span
- Location
- Liverpool, UK
- Used Product
- MIDAS CIVIL
- Modeling
- Result
- Construction
The bridge has two 40m spans and the steel pylon of 23.5m fixed on the shaped solid reinforced concrete piers on the piles.
Stayed cables are arranged in two inclined planes and the lower adjustable anchorages are located on the side of the deck.
The deck is supported by fully locked cable-stays.
Project Contact
- Engineering Consultant
- WSP | Parsons Brinckerhoff
- Address
- Kings Orchard 1 Queen Street Bristol Avon BS2 0HQ, UK
- Introduction
- Parsons Brinckerhoff is one of the world's leading engineering professional consulting firms. Their expertise ranges from environmental remediation to urban planning, from engineering iconic buildings to designing sustainable transport networks, and from developing the energy sources of the future.
- Website
- https://www.wsp-pb.com
- -