    Main features used in Liede Bridge
    • Steel box composite girder
    • Elastic catenary cable element
    • Moving load analysis
    • Temperature load analysis
    Project Information
    Owner
    -
    General Contractor
    -
    Architect
    NEXT Architects
    Engineering Consultant
    Sichuan Southwest Jiaotong University Civil Engineering Design Co., Ltd.
    Construction Period
    Completed in 2009
    Type of Project
    Self-anchored Suspension Bridge
    Size of Structure
    219m Main Span, 4.3km Total Length
    Location
    Guangzhou, China
    Used Product
    MIDAS CIVIL
    • Modeling
    • Result
    • Panorama

    Liede Bridge opened in 2009 is a bridge crossing over the Pearl River in Guangzhou, Guangdong, China. It’s a single tower self-anchored suspension bridge structure to rewrite the history of Guangzhou without a suspension bridge. The total length is 4.3km and its single tower two span 219 + 167m main span.

    Project Contact
    Engineering Consultant
    Sichuan Southwest Jiaotong University Civil Engineering Design Co., Ltd.
    Address
    No. 111, Southwest Jiaotong University Innovation Building, 18,19,20, Second Ring Road, Chengdu Jinniu District, China
    Introduction
    The firm was established in 1992. It’s the first school that opened civil engineering. Training of well-known bridge experts Mao Yisheng, Mr. Zhang Tongyan prestige, phenology experts Zhu Kezhen and the Chinese Academy of Sciences, Academy of Engineering more than 50 people in the long-span bridge research has always been a leading position in the country.