Main features used in Turda Motorway Bridge
- RC grillage wizard
- Moving load analysis with concurrent member forces
- Tendon loss results
Project Information
- Owner
- C.N.A.D.N.R. S.A.
- General Contractor
- PORR Construct
- Engineering Consultant
- INTEGRATED ROAD SOLUTIONS
- Construction Period
- 2014 – 2017
- Type of Project
- Multi-cell Box Girder Bridge
- Size of Structure
- 168m Main Span, 1.9km Total Length
- Location
- Cluj-Napoca, Romania
- Used Product
- MIDAS CIVIL
- Modeling
- Result
- Drawing/Report
The project includes planning and construction of a 16.30km long motorway section.
Within this project, 17 highway bridges of which two run over viaducts, 13 overpasses and a parking space as well as road maintenance will be built.
A total of 13 overpasses will be built on the route.
Project Contact
- Engineering Consultant
- INTEGRATED ROAD SOLUTIONS
- Address
- Str. Alexandru Lapusneanu, nr.20C, sector 1, Bucuresti 012867, Romania
- Introduction
- IRS was established in 2011. The company is specialized in design and technical checks of bridges, passages, and viaducts. They also provides stability and dynamism verification.
- Website
- https://www.irsol.ro
- office@irsol.ro