Would you like to sign out?

    Bridge

    Post-Tension Slab Analysis & Design

    BLOG NEWS & TRENDS

     

    Post-Tension Slab Analysis & Design


    Please fill out the Download Section (Click here) below the Comment Section to download the Structural Design Guide for Prestressed Slabs.

     

     

     

    Table of Contents 

     

    What is Post-Tensioning?

     

     


     

     

    What is Post-Tensioning?

     

    Post-tensioning is a technique for reinforcing concrete. Post-tensioning tendons, which are prestressing steel cables inside plastic ducts or sleeves, are positioned in the forms before the concrete is placed. Afterward, once the concrete has gained strength but before the service loads are applied, the cables are pulled tight, or tensioned, and anchored against the outer edges of the concrete.

     

    Post-tensioning is a form of prestressing. Prestressing simply means that the steel is stressed (pulled or tensioned) before the concrete has to support the service loads. Most precast, prestressed concrete is actually pre-tensioned-the steel is pulled before the concrete is poured. Post-tensioned concrete means that the concrete is poured and then the tension is applied-but it is still stressed before the loads are applied so it is still prestressed.

     

    Advantages & Applications of Post-Tensioning

     

     
    Post tension analysis & design_1
     
                      * It reduces or eliminates shrinkage cracking-therefore no joints, or fewer joints, are needed.
                     * Cracks that do form are held tightly together.
                     * It allows slabs and other structural members to be thinner.
                     * It allows us to build slabs on expansive or soft soils.
                     * It lets us design longer spans in elevated members, like floors or beam.
     
     

     

    Post-Tension Type

     

    bonded pos-tensioning and nbonded post-tensioning

     

    (a) Bonded Post-Tensioning
    It is used for large structural elements such as beams and transfer girders, design advantages include increased span lengths and load carrying capacity and reduced deflection.

     

    (b) Unbonded Post-Tensioning
    It is typically used in new construction for elevated slabs, slabs-on-grade, beams, and transfer girders, joists, shear walls, and mat foundations. Light and flexible, the unbonded mono strand can be easily and rapidly installed – providing an economical solution.

     

     

    Strength of Prestressing Steel

     

     

     

     

    pt slab jacking stage and service stage

    Figure 1: Wheel load dispersion; hc < 2 ft) - Source: AASHTO LRFD
     

     

    Step Immediately after prestressing After anchoring
    Tension Stress Min[ 0.94 fpy, 0.80 fpu ] 0.70 fpu
     

     
    Diameter Aps (mm2) fpu (Mpa) fpy (Mpa) fpe (Mpa) Fst (kN) Fse (kN)
    12.7mm
    98.71 1,860 1,674 1,200 146 118.4
    15.2mm 138.7 1,860 1,674 1,200 205 166.4

     

     

    Aps : Area of prestressing steel

    fps : Stress in prestressed reinforcement at nominal strength
    fpu : Specified tensile strength of prestressing steel
    fpy : Specified yielding strength of prestressing steel (0.90* fpu= 0.90*1,860Mpa = 1,674Mpa)
    fpi : Initial prestress stress of prestressing steel
    fpe : Effective prestress stress of prestressing steel (0.65* fpu= 0.65*1,860Mpa = 1,200Mpa)
    Fst : Max. prestress force ( Min[ 0.94 fpy, 0.8 fpu ] *Aps = Min[ 1,573 or 1,485 ] *138.7 = 205kN )
    Fse : Effective prestress force ( fpe*Aps = 1,200Mpa*138.7 = 166.4kN )
    Fps : Ultimate prestress force

     

     

    Design Steps

     

     

    PT SLAB Design Step

     

    post-tension member and tendon removed

    Figure 3: Wheel load dispersion (Overlapping dispersion area); hc > 2 ft - Source: AASHTO LRFD

     

             (a) Post-tensioned member                                               (b) Tendon removed

                                                                                                                                     Step 1: Jacking Stage (Fst)

                                                                                                                                     Step 2: Transfer Stage (Fpi)

     

     

    service codition and strength condition

     

     

                                            (c) Service condition (SLS)                                                  (d) Strength condition  (ULS)

                                               Step 3: Service Stage (Fse)                                                     Step 4: Ultimate Stage (Fps)

     

     

    After Jacking Stage

    • Activity of anchorage device
    • Tension force loss due to friction
    • Tension loss due to elastic shrinkage of concrete

     

    AfterTransfer Stage
    • Tension loss due to creep
    • Tension loss due to shrinkage
    • Tension loss due to strand relaxation

     

     

    Loading Conditions

     

    Loading Conditions-1

     

     

    Transfer Stage

    • Using Prestress Force → Fsi (before short/long-term tension loss occurs, Max. prestress)
    • Using Concrete strength : fci (compressive strength of concrete when prestress is introduced, Min. strength)
    • Loading : only Self-weight (before adding a finishing and live loads)
    • Checking item : Tensile cracking and crushing of concrete, failure of anchorage part.

     

    Service Stage

    • Using Prestress Force  → Fse (Effective tension after short/long-term tension loss occurs)
    • Using Concrete strength : fck (Max. design strength)
    • Loading : All design load (Unfactored Load)
    • Checking item : Deflection, Crack Width.

     

    Ultimate Stage

    • Using Prestress Force → Nominal Strength
    • Using Concrete strength : fck (Max. design strength)
    • Loading : All design load (Factored loads)
    • Checking item : Flexural failure or compression stress under flexural behavior.

     

     

     

    Definition of Member Forces

     

     

    Example 1: Continuous Beam

     

    primary moment

    MS : Moment due to own weight of concrete section.
    MO : Moment due to other applied loads.

    M1 : Primary moment → Moment by the distance between the section center and the prestressing point.

    In example 1: M = Prestressing force x Eccentricity distance = P x -e = -Pe

    Δ : Deflection by M1 →Deflection at point B when considered as a simple beam.

    In example 1 : "Δ"=(Mol2 )∕8EI= (Pe(2l)2 )∕8EI=(Pel2 )∕2EI

    R : Reaction by Δ → Point B should not be deflected by the support, so a reaction force is generated so that deformation as much as (-)Δ occurs.

     

    In example 1 :  

    이미지 49

    secondary moment

     

    MSecondary : Secondary Moment → Moment caused by R
    * MSecondary means the moment created by the reaction force that restrains the deformation caused by M1.

    In example 1 :  𝑀𝑆𝑒𝑐𝑜𝑛𝑑𝑎𝑟𝑦 𝑎𝑡 𝑝𝑜𝑖𝑛𝑡 𝐵=(3𝑃𝑒/2𝑙)×𝑙=3𝑃𝑒/2

    MNet : Net final Moment = M1 + MSecondary : Moment acting on the actual continuous beam by prestressing.

    In example 1 : 𝑀u 𝑎𝑡 𝑝𝑜𝑖𝑛𝑡 𝐵=−𝑃𝑒+(3𝑃𝑒/2)=𝑃𝑒/2

     

     

    Thickness or Depth of Section

     

    PT SLAB

    <Thickness-span correlation by each slab system>

     

    • RC Member

    Span/Depth Continuous span Simple span
    Beam 21 16
    2-way slab 30 -
    1-way slab 28 20

     

     

    • Post Tension Member

    Span/Depth Continuous span Simple span
    Roof Not Roof Roof Not Roof
    Beam 60% 70% 53% 62%
    2-way slab 63% 71% - -
    1-way slab 56% 62% 44% 50%

     

     

    • Reduction ratio of thickness or depth when PT is applied

    RC/PT (%) Continuous Span Simple span
    Roof Not Roof Roof  Not Roof
    Beam 60% 70% 53% 62%
    2-way slab 63% 71% - -
    1-way slab 56% 62% 44% 50%

     

     

    The thickness is reduced by 30-50% compared to the RC member. Alternatively, an economical design can be made by reducing the amount of rebar or tendon required for the same thickness.

     

     

     

    Post-Tension Slab Procedure

     

    Step 01 : Installing slab formwork

    intalling slab formwork

    Step 02 : Installing slab rebar

    installing slab rebar

     

    Step 03 : Placing bar chair by profile height

    placing bar chair by profile height

     

    Step 04 : Placing tendon on the bar chair

    Step 04  Placing tendon on bar chair

    Step 05 : Add extra rebar

    Step 05  Add extra rebar

    Step 06 : Pouring concrete

    Step 06  Pouring concrete

    Step 07 : Insert block and jaws bar chair

    Step 07 Insert block and jaws bar chair

    Step 08 : Stressing and measuring elongation

    Step 08  Stressing and measuring elongation

    Step 09 : Grouting

    Step 09  Grouting

     

     

     

    Design Flow Chart for Post-Tension

     

     

    Design Flow Chart for Post-Tension

     

    1. Choose Tendon force and profile

    Tendon Profile Type

    Tendon Profile Type

    How to arrange tendon of parabolic shape

    How to  arrange tendon of parabolic shape_1

     

    How to  arrange tendon of parabolic shape_2

     

    After Transfer Stage

     

    How to  arrange tendon of parabolic shape_3

     

    2. Check final stresses and Check initial stresses

     

    Allowable stress for Concrete                                                                                                                                         unit : (MPa)

    Checking Stage Conditions Allowable stress
    under Initial Service Load (Initial) 1. Extreme fiber stress in compression pci = 0.60 fci
    2. Extreme fiber stress in tension pti = 0.25 fci0.5
    3. Extreme fiber stress in tension at ends of simply supported members pti = 0.50 fci0.5
    under Service Load (Final) 1. Extreme fiber stress in compression (at Long-Term Service Load) pcf = 0.45 fck
    2. Extreme fiber stress in compression (prestress + total load) pcf = 0.60 fck
    3. Extreme fiber stress in tension ptf = 0.50 fck0.5

     

    Allowable stress for Tendon (Strand)                                                                                                                          unit : (MPa)

    Checking Stage Conditions Allowable stress
    During Stressing - Max [0.94 fpy, 0.8fpu]
    Immediately after stressing - 0.70fpu

     

    Please download the white paper of Structural Design Guide for Prestressed Slabs below to see the full contents. 

     

    Subscribe to Newsletter

    Catch the weekly engineer news!

    About the Author
    Young-il Seo | Principal Structural Engineer

    Young-il has over 13+ years of experience in building design, especially high-rise buildings with column reduction analysis, plant structures, pushover analysis, health monitoring, and vibration control projects. Since 2016, he is planning and providing technical supports for midas building products such as midas Gen, nGen, and Design+.

    DOWNLOAD Structural Design Guide
    for Prestressed Slabs

    Chapter 1. What is post-tensioning
    Chapter 2. Design Flow for Post-Tension
    Chapter 3. Post-Tension Design Tip and Example
    Chapter 4. Tutorial forPost-Tension Beam

    All

    What you may
    also like

    Subscribe to Newsletter

    Catch the weekly engineer news!