[Righter's Story] Xiao Fu "A change in one cable affects the entire system"

Written by Team MIDAS | Oct 17, 2026, 3:00:03 PM

Expertise · AECOM

Xiao Fu is Complex Bridge Lead for the US West at AECOM. On the Mobile River Bridge project, every cable that went in changed the forces in the ones already there, and the numbers in the model still had to become steps a crew could follow on site. The story below is how Xiao Fu closed that gap. 

In Xiao Fu's own words.

"I always try to understand whether the analysis and assumptions make sense from a real-world structural and construction perspective, rather than simply relying on what the software says."

There have been many situations where the initial results did not immediately make sense. Instead of simply accepting the output, I learned to use the model to investigate the load path, test different assumptions, and understand what was actually driving the response. What I value most is not simply the ability to obtain an analysis result, but the ability to use the model to understand the underlying structural behavior.

Every cable affects the whole bridge

One example was my work on construction-stage cable tuning for the Mobile River Bridge. The challenge was to determine the appropriate cable forces during construction so that the bridge could achieve the intended geometry and structural response as the different construction stages progressed.  On this bridge, everything was highly interdependent. A change in one cable or construction step could shift the deck geometry, the pylon behavior and the forces in the cables already installed, affecting the response of the entire system. 

I approached the problem by carefully reviewing the construction sequence and using the global analysis model to evaluate the effects of each cable-tuning step. Rather than treating the calculated cable forces as isolated values, I looked at the overall structural response and how the tuning affected the deck elevations, pylon forces, and load distribution through subsequent construction stages.

A tuning strategy the crew could carry out

My experience with complex bridge analysis helped me identify the appropriate tuning strategy and distinguish between theoretical model results and behavior that would be practical to achieve during construction. The final tuning approach provided the contractor and design team with a practical means of controlling the bridge geometry and structural response during construction while maintaining the intended final condition.

Q. You now work directly with the MIDAS team on problems that come up on live projects. What does that look like?

It helps address practical challenges encountered on complex bridge projects and align software functionality with real engineering applications. Seeing an issue that comes up on a real project turn into an improvement or better capability in the software has been particularly rewarding.

Xiao Fu weighed every cable-tuning step against what a crew could actually carry out, and the contractor got a tuning approach it could use. When your next model gives a clean answer, would you check it once more ?